Project Description
Service: Refurbishment & Reinstatement Works
F1 Sepang Racing Circuit ( 8000 m2 )
Project Objective
To remove 10mm – 12mm of the screed and water proofing membrane, profiling, and exposing the existing concrete surface for the refurbishment of new water proofing system.
How We Help
SGI mobilized 2 units of Parana P2400 Milling machines to complete the job within 17 days which otherwise would have took more than 2-3 months to complete via conventional hacking
Savings to Main Contractors includes quick turn around time, material cost savings and sound structural integrity and drastic reduction manpower deployment.